Project Information:
At the July 18, 2025 City Council meeting, a preparation of a feasibility study for 2026 street infrastructure improvements was authorized. This project will begin in the spring of 2026. A map of impacted streets can be viewed below. Residents on streets impacted by project improvements will receive further details in the mail.
The project map identifies streets scheduled for either a reclaim and overlay, or mill and overlay pavement improvements.
Reclaim and Overlay Pavement Improvements:
A reclaim and overlay is a type of pavement improvement that involves grinding down the entire pavement section of the roadway down to the underlying gravel base. Roadways will remain gravel while the contractor performs subgrade repairs on the road base. Roadways will then be re-paved with a full new section of pavement.
Mill and Overlay Pavement Improvements:
A mill and overlay is a type of pavement improvement that involves removing only the top two to three inches of pavement. Roadways will still have a paved driving surface while the contactor performs subgrade repairs on the underlying asphalt. Following subgrade repairs to the underlying asphalt, the road will be re-paved.