May 1, 2025: Due to weather related delays this week, the contractor will be working on setting up the containment system this weekend on both Saturday, May 3 and Sunday, May 4. Once the containment system is installed, sand blasting and painting operations will begin.
April 14, 2025: The contractor Classic Protective Coatings will begin work on this project April 21, weather permitting.